Paystruct

Submit valid payment claims

The only software built from the ground up for subcontractors and main contractors to comply with the Building Industry Fairness (Security of Payment) Act 2017 (Qld).

Works with the contracts you already use
AS 4000-1997General conditions of contractAS 2124-1992General conditions of contractAS 4902-2000General conditions of contract for design and constructAS 4300-1995General conditions of contract for design and constructAS 4901-1998Subcontract conditionsAS 4903-2000Subcontract conditions for design and constructAS 2545-1993Subcontract conditionsAS 4905-2002Minor works contract conditions, Superintendent administeredAS 4906-2002Minor works contract conditions, Principal administeredAS 4122-2010General conditions of contract for consultantsAS 4915-2002Project management, general conditionsAS 4916-2002Construction management, general conditionsAS 4917-2003Construction management trade contract, general conditionsABIC MW 2018Major Works contractABIC SW 2018Simple Works contractPC-1 1998Property Council of Australia project contractNEC3 and NEC4Engineering and Construction ContractBespoke subcontractsWhatever your head contractor put in front of you

A substantial portion of payment claims are found to be invalid

A substantial portion of payment claims in Queensland are found to be invalid at adjudication or in court.

So even where a claimant has a legitimate claim to money, a respondent can avoid liability to pay it on the ground that the claim did not comply with the BIF Act.

Adjudications where the claimant recovered nothing

Queensland, by year of decision

0%10%20%30%40%50%Significant BCIPA amendmentsBIF Act20052007200920112013201520172019202120232025

11 years since 2015 average 34%. Counted from published Queensland adjudication decisions. A decision counts as nothing where the adjudicated amount is nil, which is not always a jurisdictional finding. 2026 is excluded because decisions for it are still being published.

What Paystruct serves

Every page below is the app’s own output, produced from a worked example rather than drawn for a website.

Cover letter (optional)

A4 portrait

Cover letter (optional)

Addressed to the respondent, on your letterhead, stating the claim number, the contract it is made under and the amount sought. It says in terms that the document is a payment claim under the Act and that payment of the claimed amount is requested, so neither limb of s 68(1) is left to inference.

Summary page

A4 landscape

Summary page

Who is claiming, who is being claimed against, and how much. Both parties in full, with ABNs and addresses for service; the contract, project and site; the claim number, period and date, and the date payment falls due. The claimed amount is stated once, including GST and with the GST shown separately, and the request for payment sits directly under it.

Part 1: Claim summary

A4 landscape

Part 1: Claim summary

The arithmetic, in the order it happens. Contract works, then variations split into approved and unapproved, then retention withheld and released, then other adjustments, then GST. Every column reconciles to the parts behind it, so a respondent checking the total is checking your working, not guessing at it.

Part 2: Contract works

A4 landscape

Part 2: Contract works

The schedule of works as claimed, item by item. Each line carries its unit, rate and contract amount, what was previously claimed, scheduled and paid, and what is claimed now, in dollars and in quantity. Quantities matter: a line described by a percentage alone does not identify construction work.

Part 3: Variations

A4 landscape

Part 3: Variations

Variations kept apart from the contract works and, within that, approved kept apart from unapproved. A respondent can accept one and dispute the other without the whole claim being in issue, and the summary carries the split through to the total.

Part 4: Other adjustments (optional)

A4 landscape

Part 4: Other adjustments (optional)

Delay costs, rise and fall, prime cost and provisional sum adjustments, back-charges: the entitlements that are neither a works item nor a variation. Stated as their own part so they are visible rather than folded into a works line where nobody finds them.

Part 5: Security (optional)

A4 landscape

Part 5: Security (optional)

What the respondent holds and on what footing: cash retention against the cap the contract sets, and bank guarantees or bonds with their references and expiry dates. Stated for information, because security is not a deduction from the claimed amount except where the summary shows it as one.

Part 6: Insurances (optional)

A4 landscape

Part 6: Insurances (optional)

The policies the contract requires, with insurer, policy number and expiry date. Currency of insurance is a common condition of payment, and a certificate that lapsed mid-job is an easy reason to hold a payment that has nothing to do with the work.

Schedule B: Attachments

A4 portrait

Schedule B: Attachments

Everything served with the claim, numbered and listed, and then appended behind this page as part of the same document. Attachments travel with the claim rather than sitting behind a link, so what the respondent received is the same thing you can produce later.

Statutory declaration (optional)

A4 portrait

Statutory declaration (optional)

The declaration many contracts make a condition of payment: that workers and subcontractors have been paid. It ends in a jurat, with the declarant, the place and the date, and space for the witness and their qualification, because a declaration nobody witnessed is not one.

Paystruct is built for compliance

Most payment platforms in the construction market are project administration tools. Many are built to standardise claims so the party assessing them has less to do.

Paystruct is built the other way around: to help you meet the requirements of a payment claim, for the claimant’s benefit.

01The right to claim

A reference date arises

s 75(4)

A payment claim hangs off a reference date, and only one claim may be given for each one. Serve a second claim against a date already used and the whole claim can fall over, however good the work behind it.

Paystruct works the reference dates out from your contract’s own mechanism, records which ones have been claimed, and stops you serving a second claim against a date already used.

Read more about this requirement
02What the claim must doall three, not one of three

Identify the work claimed for

s 68(1)(a)

The claim must identify the construction work, or related goods and services, it relates to. A respondent has to be able to tell what they are being asked to pay for.

Line items carry quantities and units, not percentages alone, and the review flags any description that would leave a respondent guessing.

Read more about this requirement

State the claimed amount

s 68(1)(b)

The claim must state the amount the claimant says is payable for the progress payment.

The claimed amount is computed from the breakdown and stated on the face of the claim, with the arithmetic reconciling to the line items behind it.

Read more about this requirement

Request payment

s 68(1)(c)

The claim must request payment of the claimed amount. A document that sets out a figure without asking to be paid may not be a payment claim at all.

Every claim Paystruct produces requests payment in terms, so the limb is never the thing that fails.

Read more about this requirement
03When it may be given

Given within time

s 75(2) and (3)

A claim may be given only within the period the contract allows or six months after the work was last carried out, whichever is later. A final claim runs on its own longer clock.

Paystruct counts the window from your own contract and tells you where a claim sits in it before it goes, including the longer window that applies to a final claim.

Read more about this requirement
04How it is given

Served properly

s 102

A claim only bites when it has been given to the respondent in a way the Act and the contract allow. Service is also where every later deadline is measured from.

Service methods come from the contract’s own notice provisions, and the date, method and proof are recorded against the claim.

Read more about this requirement
05What your contract adds on topwhere the contract requires them

Statutory declaration

Your contract

Many contracts make a declaration about payment of workers and subcontractors a condition of payment. It is a contractual requirement, not a statutory one, but a claim can be perfectly valid under the Act and still go unpaid for want of it.

Where the contract calls for one, Paystruct produces it alongside the claim and serves it as part of the same pack.

Read more about this requirement

Evidence of insurance

Your contract

Currency of insurance is a common condition of payment. Certificates expire mid-job, and a lapsed one is an easy reason to hold a payment.

Policies and expiry dates sit on the contract, and current certificates go out with the claim.

Read more about this requirement

Retention and security

Your contract

Cash retention, bank guarantees and bonds are governed by the contract: how much is withheld, when it is released, and what has to happen first.

Retention accrues against the cap the contract sets, releases are tracked, and instruments are held against the contract with their expiry dates.

Read more about this requirement
Sections are of the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The last group is contractual rather than statutory: a claim can satisfy the Act completely and still go unpaid because the contract asked for something else as well. Paystruct is software, not a law firm, and this is not legal advice.

Built for compliance

Three things have to be right before a claim goes out: what is in it, whether it meets the requirements on its face, and when it is served. Paystruct handles each of them in turn.

Build the claim from the contract

The breakdown lives on the contract, so every claim starts from the same items and the same numbering. You enter progress; the arithmetic follows.

  • Quantities and units on every line, not percentages alone
  • Previously claimed, this claim and claimed to date always reconcile
  • Variations, adjustments and retention carried through automatically
  • Your item numbering, headings and sub-items kept intact
Schedule of works
Carried from the contract, claim to claim
RefDescriptionQtyProgressThis claim
2.0Bulk earthworks1,240 m³100%$12,410.00
3.0In-ground services318 m85%$48,720.00
3.1Stormwater, RCP 37596 m60%$14,880.00
4.0Concrete structure412 m³60%$96,300.50
V-02Rock excavation210 m³100%$18,890.00
This claim incl. GST$184,254.92

Check it against the requirements

Before anything is served, Paystruct works through what the legislation asks of a payment claim on its face, and shows the section it is working from.

  • Reference dates worked out from the contract, and checked against earlier claims
  • Timing measured in business days, on the calendar for your State
  • Descriptions tested for whether they identify the work
  • Anything it cannot decide is put to you rather than assumed
Before you serve
Payment Claim PC-04
1 to fix
  • Reference date 28 February is valid under the contract and has not been claimed befores 75
  • Served within six months of the work being carried outs 75(4)
  • Claim states the amount claimed and requests payments 68(1)
  • Two lines are described by percentage alone and do not identify the works 68(1)(a)
  • Supporting statement attacheds 75(3)

Know where you stand on dates

Once a claim is served the clock is running. The calendar shows what has been served, what is owed back, and how long is left to respond.

  • Response window counted from the date served
  • Public holidays and the December shutdown excluded
  • A running position on every contract, not one claim at a time
  • The date, method and proof of service kept against the claim
March 2026
Business days, excluding public holidays
M
T
W
T
F
S
S
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Reference date28 February
Claim served2 March
Schedule due16 March
No payment schedule received. 3 business days left of the response period.

Set the contract up once

The contract holds the parties, the dates, the security and the breakdown. After that a claim is a period and a set of figures, not a document rebuilt from scratch.

01

Set up the contract

Parties, State, reference dates, retention and the schedule of works. Upload the contract and have the terms read out of it, or enter them yourself.
02

Build the claim

Enter progress against each item as a quantity, a percentage or a dollar figure. Variations, adjustments and retention come through from the contract record.
03

Check it before it goes

Paystruct works through the requirements it can check, and asks you about the ones that depend on facts only you have.
04

Serve it and record it

Export the claim pack, serve it the way your contract allows, and record the date, the method and the proof against the claim.

Built for claimants

Whoever is making the claim, up the chain or down it.

For subcontractors

Claim what you are owed, on time, every month.

Read more

For head contractors

Claims up the chain, obligations down the chain.

Read more

Our moat is serving claimants

Here is what each of the usual ways of putting a claim together does and does not do.

 PaystructGeneric invoicing softwareClaim portal run by the party paying youSpreadsheet
Built specifically for use by claimants under construction contractsYes✓No✕Partly–Yes✓
Built specifically for compliance with the Building Industry Fairness (Security of Payment) Act 2017 (Qld)Yes✓No✕Partly–No✕
Manages and diarises reference dates and payment schedule due datesYes✓No✕No✕No✕
Automatically standardises claims and pre-fills from current progress based on the previous claimYes✓No✕Yes✓Yes✓
Reviews draft payment claims before submission and identifies potential areas for improvementYes✓No✕No✕No✕
Automatically generates supporting statements and statutory declarationsYes✓No✕No✕No✕
Packages attachments as appendices to the payment claim rather than hyperlinksYes✓No✕No✕No✕

A general description of common approaches, not a statement about any particular product.

Common questions

Which legislation does Paystruct work to?

The Building Industry Fairness (Security of Payment) Act 2017 (Qld). Reference dates, response windows, business days and section references all follow it, and a contract is set up against the Queensland calendar, including the local show holiday for its district.

Does Paystruct tell me whether my claim is valid?

No, and you should be sceptical of anything that says it does. Whether a claim is valid turns on your contract, the facts and the legislation. What Paystruct does is work through the requirements that can be checked from your own data, put the ones that depend on your facts in front of you before anything is served, and keep the record of what went out and when.

Is this legal advice?

No. Paystruct is software. It is not a law firm and does not act for you. For a contested claim, a final claim, a terminated contract or an adjudication, get a lawyer.

Do I have to move everything across to start?

No. Set up one contract and make one claim. If the job is already running, upload the claims you have already served and Paystruct builds the breakdown and the history from them, so your numbering carries on where it left off.

What counts as a contract?

One head contract or subcontract, with its own parties, dates, security, breakdown and claim history. Separable portions of the same contract are not counted separately.

What does it cost?

Your first contract is free. Every contract after that is $49 per month, excluding GST, with every feature included and no fee per claim. See pricing.

Can I still use my own claim format?

The claim pack is built from your contract breakdown, so it carries your item numbering, your descriptions and your attachments. The cover letter, the summary and the supporting statement are all editable before anything is served.

What happens to my records if I stop paying?

They stay yours. Claim packs and the record behind them export as PDFs at any time, so the history of what you served and when does not sit only inside Paystruct.

Set up your first contract

Easy to use. Have a claim ready to serve today.