Paystruct

Submit valid payment claims

The only software built from the ground up for subcontractors and main contractors to comply with the Building Industry Fairness (Security of Payment) Act 2017 (Qld), the Building and Construction Industry Security of Payment Act 1999 (NSW), and the Building and Construction Industry Security of Payment Act 2002 (Vic).

Payment Claim PC-04
Riverside Industrial Estate, Stage 2
1 to fix
2.0Bulk earthworks1,240 m³$12,410.00
3.0In-ground services318 m$48,720.00
4.0Concrete structure412 m³$96,300.50
V-02Rock excavationApproved$18,890.00
This claim incl. GST$184,254.92
Checked against the Act
  • Reference date 28 February is valid under the contract and has not been claimed befores 75
  • Served within six months of the work being carried outs 75(4)
  • Claim states the amount claimed and requests payments 68(1)
  • Two lines are described by percentage alone and do not identify the works 68(1)(a)
  • Supporting statement attacheds 75(3)
Works with the contracts you already use
AS 4000-1997General conditions of contractAS 2124-1992General conditions of contractAS 4902-2000General conditions of contract for design and constructAS 4300-1995General conditions of contract for design and constructAS 4901-1998Subcontract conditionsAS 4903-2000Subcontract conditions for design and constructAS 2545-1993Subcontract conditionsAS 4905-2002Minor works contract conditions, Superintendent administeredAS 4906-2002Minor works contract conditions, Principal administeredAS 4122-2010General conditions of contract for consultantsAS 4915-2002Project management, general conditionsAS 4916-2002Construction management, general conditionsAS 4917-2003Construction management trade contract, general conditionsABIC MW 2018Major Works contractABIC SW 2018Simple Works contractGC21 Edition 2NSW Government general conditions of contractPC-1 1998Property Council of Australia project contractNEC3 and NEC4Engineering and Construction ContractBespoke subcontractsWhatever your head contractor put in front of you

More than a third of adjudications end with nothing

Across 1,582 Queensland adjudication decisions made under the current Act, 567 ended with the claimant recovering nothing at all. Not reduced. Nothing.

Under the Act it replaced, that figure was one in seven. It has since held at about one in three, and the last two and a half years look the same as the ten before them.

Counted from 7,601 Queensland adjudication decisions published between November 2004 and June 2026. A nil decision is not always a jurisdictional one; what these numbers measure is the money recovered.

35.8%
recovered nothing under the current Act
15.3%
under the Act it replaced
7,601
decisions counted, 2004 to 2026

Built for compliance

Three things have to be right before a claim goes out: what is in it, whether it meets the requirements on its face, and when it is served. Paystruct handles each of them in turn.

Build the claim from the contract

The breakdown lives on the contract, so every claim starts from the same items and the same numbering. You enter progress; the arithmetic follows.

  • Quantities and units on every line, not percentages alone
  • Previously claimed, this claim and claimed to date always reconcile
  • Variations, adjustments and retention carried through automatically
  • Your item numbering, headings and sub-items kept intact
Schedule of works
Carried from the contract, claim to claim
RefDescriptionQtyProgressThis claim
2.0Bulk earthworks1,240 m³100%$12,410.00
3.0In-ground services318 m85%$48,720.00
3.1Stormwater, RCP 37596 m60%$14,880.00
4.0Concrete structure412 m³60%$96,300.50
V-02Rock excavation210 m³100%$18,890.00
This claim incl. GST$184,254.92

Check it against the requirements

Before anything is served, Paystruct works through what the legislation asks of a payment claim on its face, and shows the section it is working from.

  • Reference dates worked out from the contract, and checked against earlier claims
  • Timing measured in business days, on the calendar for your State
  • Descriptions tested for whether they identify the work
  • Anything it cannot decide is put to you rather than assumed
Before you serve
Payment Claim PC-04
1 to fix
  • Reference date 28 February is valid under the contract and has not been claimed befores 75
  • Served within six months of the work being carried outs 75(4)
  • Claim states the amount claimed and requests payments 68(1)
  • Two lines are described by percentage alone and do not identify the works 68(1)(a)
  • Supporting statement attacheds 75(3)

Know where you stand on dates

Once a claim is served the clock is running. The calendar shows what has been served, what is owed back, and how long is left to respond.

  • Response window counted from the date served
  • Public holidays and the December shutdown excluded
  • A running position on every contract, not one claim at a time
  • The date, method and proof of service kept against the claim
March 2026
Business days, excluding public holidays
M
T
W
T
F
S
S
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Reference date28 February
Claim served2 March
Schedule due16 March
No payment schedule received. 3 business days left of the response period.

Set the contract up once

The contract holds the parties, the dates, the security and the breakdown. After that a claim is a period and a set of figures, not a document rebuilt from scratch.

01

Set up the contract

Parties, State, reference dates, retention and the schedule of works. Upload the contract and have the terms read out of it, or enter them yourself.
02

Build the claim

Enter progress against each item as a quantity, a percentage or a dollar figure. Variations, adjustments and retention come through from the contract record.
03

Check it before it goes

Paystruct works through the requirements it can check, and asks you about the ones that depend on facts only you have.
04

Serve it and record it

Export the claim pack, serve it the way your contract allows, and record the date, the method and the proof against the claim.

Built for claimants

Whoever is making the claim, up the chain or down it.

For subcontractors

Claim what you are owed, on time, every month.

Read more

For head contractors

Claims up the chain, obligations down the chain.

Read more

How people do this today

Most claims are put together in something that was never built for it. Here is what each approach does and does not give you.

 PaystructGeneric invoicing softwareClaim portal run by the party paying youSpreadsheet
Built around a contract breakdown that carries claim to claimYesNoPartlyPartly
Reference dates and response windows worked out for youYesNoPartlyNo
Business days counted on your State’s calendarYesNoPartlyNo
Checks the claim before it is servedYesNoNoNo
Supporting statement produced with the claimYesNoPartlyNo
Claim pack with attachments appended in one documentYesNoPartlyNo
Record of what was served, when and howYesPartlyPartlyNo
You keep the record if the relationship endsYesYesNoYes
Works the same across Qld, NSW and VicYesNoNoNo

A general description of common approaches, not a statement about any particular product. Paystruct is software, not a law firm, and nothing here is legal advice.

Common questions

Which States does Paystruct cover?

Queensland, New South Wales and Victoria. Each has its own rules, and they are not the same: Queensland works on reference dates, New South Wales removed them in the 2018 amendments, and Victoria moved to a similar model in the 2026 reforms. A contract is set up under one State and the dates, wording and section references follow it.

Does Paystruct tell me whether my claim is valid?

No, and you should be sceptical of anything that says it does. Whether a claim is valid turns on your contract, the facts and the legislation. What Paystruct does is work through the requirements that can be checked from your own data, put the ones that depend on your facts in front of you before anything is served, and keep the record of what went out and when.

Is this legal advice?

No. Paystruct is software. It is not a law firm and does not act for you. For a contested claim, a final claim, a terminated contract or an adjudication, get a lawyer.

Do I have to move everything across to start?

No. Set up one contract and make one claim. If the job is already running, upload the claims you have already served and Paystruct builds the breakdown and the history from them, so your numbering carries on where it left off.

What counts as a contract?

One head contract or subcontract, with its own parties, dates, security, breakdown and claim history. Separable portions of the same contract are not counted separately.

What does it cost?

Your first contract is free. Every contract after that is $49 per month, excluding GST, with every feature included and no fee per claim. See pricing.

Can I still use my own claim format?

The claim pack is built from your contract breakdown, so it carries your item numbering, your descriptions and your attachments. The cover letter, the summary and the supporting statement are all editable before anything is served.

What happens to my records if I stop paying?

They stay yours. Claim packs and the record behind them export as PDFs at any time, so the history of what you served and when does not sit only inside Paystruct.

Set up your first contract

The first one is free. You can have a claim ready to serve today.